Fabiano asks: Is it possible to register and to begin a (LEED) certification process of a 40% completed project? If it is possible, what are the considerations and constraints that I need to take into account?

Answer:
Share


Hello Fabiano. Thank you for your question concerning the timeline for registering a project for LEED certification.

I will assume that you are referring to a LEED New Construction (LEED-NC) project, so I will reference that rating system. However, the other LEED rating systems are very similar. The only one that varies significantly is the LEED Existing Buildings: Operation and Management (LEED-EBOM) rating system.

LEED Project Registration

According to the LEED Certification Policy Manual dated June 17, 2011, it is possible to begin the LEED certification process while the project is already in the construction phase. There are two paths for LEED project registration.

Standard Review

The first path for LEED registration is the Standard Review, which is a combined design and construction review. Applications for the review must be submitted within two years of substantial completion (which is defined as the date on which the building receives a Certificate of Occupancy). The application must also be submitted before the LEED-NC rating system Sundown date, which is still to be determined for LEED-2009.

Split Review

The second path for LEED registration is the Split Review, in which there are separate design and construction reviews. For this registration path, the application for design review must be submitted before substantial completion. The application for construction review must be submitted following the completion of the Design Review phase and within 2 years of substantial project completion.

LEED Credits: Design Phase vs. Construction Phase

One consideration you’ll need to make is that certain LEED credits, such as some of the Sustainable Sites, Water Efficiency and Energy Efficiency credits, are typically determined in the design phase. If the design of your project did not take these credits into account, you may have a problem achieving enough points for LEED certification.

Also, you should check that you have met the necessary prerequisites and Minimum Program Requirements for the LEED-NC rating system. Typically, a team that registered their project for LEED certification will have taken these prerequisites into account before design, which makes it easier to achieve LEED certification. If determination is made in the middle of the project, it’s more difficult to change things that were already designed and constructed in order to achieve LEED certification. It’s harder, but not impossible!

Good luck!

Related Advice:

Expert Advice and Comments

windows 7office 2010

We realize, WindowsVista began, the device carries a built-in tool called “captured picture of components,”office 2010 can partially replaced third-party screenshots tools, office 2010 the good news is we could office 2010 directly in complete screenshots operation, can say is much more convenient. Switch the signal from office 2010 Word2010 or Excel 2010 “Insert” TAB, we could maintain “written” functional groups called office 2010 “found a Screenshot” button, here to compliment multiple screenshots mode, click “Screenshot” button, we are able to be found here current opened a window, click on the screenshots picture after inserting the latest document might be selected.If choose “ScreenClipping”, office 2010 return can find desktop mouse cursor had become a fine cross, press the mouse left key can intercept corresponding picture, loosen the mouse can return to document window, just intercepted images may be automatically entered into the latest document. Whether or not this was in office 2010 PowerPoint2010 demo manuscripts window, switch to “Insert” TAB, “Screenshot” office 2010 button position gone to live in “aptly titled”office 2010 functional groups, we may also rapid Insert the present window here the thumbnail or intercept window.office 2010 Skills 2: eliminate the background picture Already insert Word document to the pictures, you can easily get rid of the background picture, so that they don’t could do with huge PhotoShop, more is much better still can also add or remove the watermark. Choose photos, plunge to office 2010 “PictureTools TAB, called” is found here BackgroundRemoval “button and then click on” BackgroundRemoval office 2010 “button, you’ll soon put would like to mark out the photographs, whether very magical?Skills 3: custom graphical user interface office 2010 Professional Plus gui may, based on the needs in our own definition, operation is quite simple. Click on the icon inside upper left corner Office button enter configuration panel, click “CustomRibbon”, here to all or any tabs, button customized for example can adjust each TAB position, delete option card, may will originally displayed in English for your Chinese, the object changes office 2010 as selected

Post new comment

The content of this field is kept private and will not be shown publicly.
  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <code> <ul> <ol> <li> <dl> <dt> <dd>
  • Lines and paragraphs break automatically.
  • You may use [view:name=display=args] tags to display views.

More information about formatting options